Maple Library Renovation Project Update

Construction activities at the Maple Library continued throughout December. Installation of reading garden shade structures and outdoor furniture is now complete. Sound baffles have been painted and hung. All painting work is done, and decorative film decal installation on leaf motives has begun. All CVP flooring is also complete, and preparation for carpet installation is ongoing. Glass installation of library quiet study room is in progress. All millwork pieces have been received and will be installed following carpet installation.

Reading Garden shade structure mounted in place.
Reading garden furniture has been installed.
Glass installation quiet study room in progress.
Decorative decal application on leaf stem in progress.
Decorative ceiling work outside the library’s main entrance is in progress.